The shingles went on, Monday, March 1. Someone was still on the roof, finishing up, when I left at 6:45 PM.
![](https://blogger.googleusercontent.com/img/b/R29vZ2xl/AVvXsEgc1qFF4SBf1RD9ZVP7xtZeJ2A2hV1KrDczaDJV8h84TZfN9UJPrZkH14FSyt1Ur2D4pwXxUPbwwaSkuJCC5_DMzYWdDhHlWZWhQs867juQLYXz5rY4aj24NSbRNTuEmP1XEuyVdlkJx34/s200/030310a.jpg)
On March 2nd they continued to work on the roof and did some framing for the new walls. They removed a window and boarded it up on the 3rd.
![](https://blogger.googleusercontent.com/img/b/R29vZ2xl/AVvXsEhP2yDUNYeLApZlMeJDd9QvAQBcFFzb2t7rJGSMi3ckWjLIvkgWKeF-LUdDQFGdCnvNHKjdWWGrkVdish0t7178o_bHw0hMPh7FNbGx64LPALL511tDhkVsc0CW3NSekgEd2FIx0XGRb34/s200/030510d.jpg)
Friday Troy and I had our first disagreement. The electrician had placed the switches for the room four feet away from the door. This was what was specified on his drawing but I was certain that was not what I had told Robert when we were drawing up the contract. In fact, I'm pretty sure I specified where I wanted the switches for the light and fan. It was NOT where the electrician put them.
![](https://blogger.googleusercontent.com/img/b/R29vZ2xl/AVvXsEgcJoIUUtfrqrMmrhUQKbpZ-XhJ7Z8YHGJi1zaYQV8sKSgB7zEbvYudLGNd5AaDlkVPgD3qykNTRTk5X6-AybetGRlZ8tAWrQtNKWHJH4q_0d5hwLSO5nf16Dz-TgBkKkFXrKXkbiihl38/s200/030510b.jpg)
That evening I looked at my contract papers and, sure enough, on the drawings which I approved, the light switches for the fan and light were beside the doorway - just where I had requested. Someone decided to change their location without clearing it with me first. But at least I knew the error was not mine.